Utility Scuppers

Project
Utility Company
Scuppers

Project Location
North Carolina

Industries
Industrial

Services
Exterior Renovations
Self Perform

Square Footage

Design Firm / Architect
Penta Engineering

Scope
Remove sections of the existing parapet walls to allow rain water to shed off the roof to avoid potential roof collapse in preparation of a 500 year rainfall event. parapet walls were 4′ high, up to 30′ long, and 18″ thick of pour-in-place concrete

Unique Challenges
Nine month project with complex lift plans. Saw cutting parapet walls in a critical environment around nuclear reactors and on top or critical power plant production infrastructure.